(a) CVC contract awarding activities shall ensure ordering activities are aware of proper ordering procedures, to include the best value and ordering requirements specified in paragraphs (d) and (e) below. If the CVC contracts are available for ordering through an online ordering system, then the online ordering system must inform ordering activities of the ordering requirements of this section.
(b) Ordering activities must be made aware of all available CVC sources of supply. This can be done via a number of methods, to include use of web-based resources.
(c) Orders valued at or below the micro-purchase threshold may be placed with any CVC contractor, without regard to the requirements of this section.
(d) Orders exceeding the micro-purchase threshold shall be placed with the CVC contractor that can supply the item that represents the best value to the Government. Ordering activities are required to maintain their best value determination documentation as part of their order file in accordance with (i) below. Areas that should be considered to determine best value include:
(1) Price;
(2) Item features required for effective mission performance, e.g., quality, customer/user considerations, reliability, transportability including airlift capability;
(3) Warranty considerations;
(4) Delivery requirements;
(5) Past performance;
(6) Interchangeability
(7) Environmental and energy efficiency considerations;
(8) Small business considerations;
(9) Special features of the supply or service required for effective program performance;
10) Trade-in considerations;
(11) Probable life of the item selected compared to that of a comparable item; and
(12) Maintenance and repair availability and uniformity with current equipment.
(e) Orders exceeding the micro-purchase threshold shall be placed using the following ordering procedures:
(1) Review available vendors on online electronic ordering systems or at least three CVC pricelists; and
(2) Select the best value based on (d) above
(f) Ordering offices need not seek further competition, synopsize the requirement, make a separate determination of fair and reasonable pricing, or consider small business programs.
(g) Contracting officers awarding CVC contracts have already determined the prices of items under those contracts to be fair and reasonable. By placing an order against a CVC contract using the procedures in this section, the ordering office has concluded that the order represents the best value and results in the lowest overall cost alternative (considering price, special features, administrative
costs, etc.) to meet the Government's needs.
(h) Orders placed under a CVC contract-
(1) Are not exempt from development of an acquisition plan (see FAR Subpart 7.1) and an information technology acquisition strategy (see FAR Part 39);
(2) Are not exempt from the mandatory sourcing requirements of FAR Part 8; and
(3) Must comply with all FAR requirements for a bundled contract when the order meets the definition of “bundled contract” (for the purposes of this section the definition of “single contract” used in the definition of “bundling” in FAR 2.101(b) is expanded to include an order placed against a CVC contract).
(i) Documentation:
(1) Minimum documentation is generally all that is required. Orders should be documented, at a minimum, by identifying the contractor the item was purchased from, the item purchased, and the amount paid. If an Activity requirement in excess of the micro-purchase threshold is defined so as to require a particular brand name, product, or a feature of a product peculiar to one manufacturer, thereby precluding consideration of a product manufactured by another company, the ordering office shall include an explanation in the file as to why the particular brand name, product, or feature is essential to satisfy the agency’s needs. Ordering activities shall maintain appropriate documentation for each order in their files.
(2) Orders must be reviewed on a periodic basis to determine which products represent the best value at the lowest overall cost alternative to the Government and give each CVC contractor a fair opportunity to have its products considered.