Reference

More Resources

 

Section 1807.105: Contents of written acquisition plans.


Acquisition plans shall address each applicable topic listed in FAR 7.105, as supplemented by this section. Plans shall be structured by subject heading using each italicized topic heading in the same sequence as presented in the FAR. Subheadings should be used when appropriate (e.g., the separate items under contracting considerations at 7.105(b)(4)). Topics not applicable to a given acquisition (e.g., design-to-cost and should-cost are not compatible with service acquisitions), should be marked N/A. The requirements in FAR 7.105 regarding performance-based acquisition methods shall not be limited to acquisition plans for service contracts.
(a)(1) Describe in nontechnical terms the supplies or services to be acquired. Include quantities.
(a)(2) NPR 7120.5 shall be an integral part of acquisition planning for programs and projects subject to its requirements. If the NPR does not apply, the acquisition plan shall clearly state that fact. If the NPR does apply, specify whether all required NPR 7120.5 documentation is current and approved. If not, describe the approach for obtaining approval or the authority to proceed without approval before release of draft or final solicitations. For programs and projects under the NPR, all draft or final solicitations subject to, or directly or substantially in support of, those programs or projects shall clearly identify the program or project of which they are part.
(a)(3) Identify the estimated cost and describe the estimating methodology.
(a)(5) Specify the delivery or performance period requirements separately by the basic contract, each option, and the total. Provide supporting rationale, which describes the relationship between the technical requirements and the proposed period of performance, including the basis for the decision regarding duration and the appropriateness of the inclusion of options.
(a)(7) Discuss project/program risks (see NPR 7120.5, NASA Program and Project Management Processes and Requirements). In addition to technical, schedule, and cost risks, the discussion shall include such considerations as: safety and security (including personnel, information technology, and facilities/property); the need to involve foreign sources (contractor and/or governmental), and risks of unauthorized technology transfer (see NPD 2110.1E and Export Control Program (http://www.hq.nasa.gov/office/oer/nasaecp/Welcome.html)); and resource risk, including the necessary level and expertise of NASA personnel resources available to manage the project/program. For each area of risk identified, the discussion shall include a quantification of the relative magnitude (e.g., high, medium, low) together with the specific actions taken to structure the acquisition approach to manage the risks throughout the acquisition process. For example, this discussion would identify those areas that have safety risk, discuss how safety is addressed in contract requirements and evaluated in the source selection, and how it will be managed and incentivized during contract performance. Decisions to accept, mitigate, track, and/or research risk factors shall be identified and documented as part of acquisition planning.
(a)(8) Streamlining applies to all NASA acquisitions. Describe all planned streamlining procedures.
(b)(3) Discuss the source selection approach (trade-off, lowest price technically acceptable, combination of approaches) and the rating method (numerical scoring, acceptable/unacceptable, adjectival) to be used, how it will be used and why it is expected to result in the selection of the best value to NASA. Address how cost realism will be evaluated.
(b)(4)(A) If an incentive contract is planned, describe the planned incentive(s) and the anticipated effects.
(B) Describe subcontracting issues, including all applicable subcontracting goals. (See FAR Part 19 and Part 1819).
(b)(5)(A) Identify the estimated cost separately by the basic contract, each option and total amount.
(B) Identify the funding by fiscal year and NASA Structure Management project number.
(C) Discuss planned approaches to eliminate funding shortfalls (vs. the estimated cost).
(b)(6) Identify the type of work statement/specification planned. Specifically address the applicability of performance work statements and the availability of commercial sources for the supplies/services.
(b)(10) Address contract management issues, including -
(A) Planned delegations of administrative functions; and
(B) When contract changes are anticipated, the plan to manage such changes and the specific measures that will be taken to minimize the issuance of undefinitized contract actions.
(b) (20) If the period between release of solicitation to contract award is more than 120 calendar days (180 days for formal SEB competitions), explain why that goal cannot be met.




Warning: require(/home/simplyauto/www/includes/site_footer.php): failed to open stream: Permission denied in /home/simplyauto/www/regs/fars/section.php on line 347

Fatal error: require(): Failed opening required '../../includes/site_footer.php' (include_path='.:/usr/local/lib/php') in /home/simplyauto/www/regs/fars/section.php on line 347