Reference

More Resources

 

Section 5452.216-9033: ECONOMIC PRICE ADJUSTMENT - ESTABLISHED PRICES

As prescribed in 16.203-4-90(g) use the following clause. Complete paragraph (c)(1) by entering the appropriate percentage price increase ceiling, considering the length of contract performance. Any percentage over 10 percent requires approval by the Chief of the Contracting Office.

52.216-9033 ECONOMIC PRICE ADJUSTMENT - ESTABLISHED PRICES (FEB 2009)

(a) The Contractor warrants that the unit price stated in the Schedule for _________ [offeror insert Schedule line item number] is not in excess of the Contractor’s applicable established price in effect on the contract date for like quantities of the same item. The term “unit price” excludes any part of the price directly resulting from requirements for preservation, packaging, or packing beyond standard commercial practice. The term “established price” means a price that -

    (1) Is an established catalog or market price for a commercial item sold in substantial quantities to the general public; and

    (2) Is the net price after applying any standard trade discounts offered by the Contractor.

(b) The Contractor shall promptly notify the Contracting Officer of the amount and effective date of each decrease in any applicable established price. Each corresponding contract unit price shall be decreased by the same percentage that the established price is decreased. The decrease shall apply to those items delivered on and after the effective date of the decrease in the Contractor’s established price, and this contract shall be modified accordingly.

(c) If the Contractor’s applicable established price is increased after the contract date, the corresponding contract unit price shall be increased, upon the Contractor’s written request to the Contracting Officer, by the same percentage that the established price is increased, and the contract shall be modified accordingly, subject to the following limitations:

    (1) The aggregate of the increases in any contract unit price under this clause shall not exceed ___ percent of the original contract unit price.

    (2) The increased contract unit price shall be effective -

        (i) On the effective date of the increase in the applicable established price if the Contracting Officer receives the Contractor’s written request within 10 days thereafter; or

        (ii) If the written request is received later, on the date the Contracting Officer receives the request.

    (3) The increased contract unit price shall not apply to quantities scheduled under the contract for delivery before the effective date of the increased contract unit price, unless failure to deliver before that date results from causes beyond the control and without the fault or negligence of the Contractor, within the meaning of the Default clause.

    (4) No modification increasing a contract unit price shall be executed under this paragraph (c) until the Contracting Officer verifies the increase in the applicable established price.

    (5) Within 30 days after receipt of the Contractor’s written request, the Contracting Officer may cancel, without liability to either party, any undelivered portion of the contract items affected by the requested increase, except as follows

        (i) The Contractor may, after that time, deliver any items that were completed or in the process of manufacture at the time of receipt of the cancellation notice, provided the Contractor certifies and notifies the Contracting Officer of such items within 10 days after the Contractor receives the cancellation notice.

        (ii) The Government shall pay for those items at the contract unit price increased to the extent provided by paragraph (d) of this clause.

        (iii) Any standard steel supply item shall be deemed to be in the process of manufacture when the steel for that item is in the state of processing after the beginning of the furnace melt.

(d) During the time allowed for the cancellation provided for in subparagraph (c)(5) of this clause, and thereafter if there is no cancellation, the Contractor shall continue deliveries according to the contract delivery schedule, and the Government shall pay for such deliveries at the contract unit price, increased to the extent provided by paragraph (c) of this clause.

(e) The Contractor shall certify on each invoice that each unit price stated therein reflects all decreases required by this clause and shall certify on the final invoice that all price decreases required by this clause have been applied in the manner required herein.

(f) DISPUTES. Any dispute arising under this clause shall be determined in accordance with the Disputes clause of the contract.

(End of clause)




Warning: require(/home/simplyauto/www/includes/site_footer.php): failed to open stream: Permission denied in /home/simplyauto/www/regs/fars/section.php on line 347

Fatal error: require(): Failed opening required '../../includes/site_footer.php' (include_path='.:/usr/local/lib/php') in /home/simplyauto/www/regs/fars/section.php on line 347