As prescribed by 2144.204, insert the following clause:
Subcontracts (OCT 2005)
(a) The Contractor must notify the Contracting Officer reasonably in advance of entering into any subcontract or subcontract modification, or as otherwise specified by this contract, when the cost of that portion of the subcontract that is charged the FEGLI Program contract exceeds $550,000 and is at least 25 percent of the total cost of the subcontract.
(b) The advance notification required by paragraph (a) of this clause shall include the following information:
(1) A description of the supplies or services to be subcontracted;
(2) Identification of the type of subcontract to be used;
(3) Identification of the proposed subcontract and an explanation of why and how the proposed subcontractor was selected, including the competition obtained;
(4) The proposed subcontract price and the Contractor's cost or price analysis;
(5) The subcontractor's current, complete, and accurate cost or pricing data and Certificate of Current Cost or Pricing Data, if required by other contract provisions.
(6) The subcontractor's Disclosure Statement or Certificate relating to Cost Accounting Standards when such data are required by other provisions of this contract; and
(7) A negotiation memorandum reflecting-
(i) The principal elements of the subcontract price negotiations;
(ii) The most significant consideration controlling establishment of initial or revised prices;
(iii) The reason cost or pricing data were or were not required;
(iv) The extent, if any, to which the Contractor did not rely on the subcontractor's cost or pricing data in determining the price objective and in negotiating the final price;
(v) The extent to which it was recognized in the negotiation that the subcontractor's cost or pricing data were not accurate, complete, or current; the action taken by the Contractor and the subcontractor; and the effect of any such defective data on the total price negotiated;
(vi) The reasons for any significant difference between the Contractor's price objective and the price negotiated; and
(vii) A complete explanation of the incentive fee or profit plan when incentives are used. The explanation shall identify each critical performance element, management decisions used to quantify each incentive element, reasons for the incentives, and a summary of all trade-off possibilities considered.
(c) The Contractor shall obtain the Contracting Officer's written consent before placing any subcontract for which advance notification is required under paragraph (a) of this clause. However, the Contracting Officer may ratify in writing any such subcontract. Ratification shall constitute the consent of the Contracting Officer.
(d) The Contracting Officer may waive the requirement for advance notification and consent required by paragraph (a), (b), and (c) of this clause where the Contractor and subcontractor submit an application or renewal as a contractor team arrangement as defined in FAR subpart 9.6 and-
(1) The Contracting Officer evaluated the arrangement during negotiation of the contract or contract renewal; and
(2) The subcontractor's price and/or costs were included in the plan's rates that were reviewed and approved by the Contracting Officer during negotiations of the contract or contract renewal.
(e) Unless the consent or approval specifically provides otherwise, consent by the Contracting Office to any subcontract shall not constitute a determination (1) of the acceptability of any subcontract terms or conditions; (2) of the allowability of any cost under this contract; or (3) to relieve the Contractor of any responsibility for performing this contract.
(f) No subcontract placed under this contract will provide for payment on a cost-plus-a-percentage-of-cost basis. Any fee payable under cost reimbursement type subcontracts will not exceed the fee limitations in FAR 15.404-4(c)(4)(i). Any profit or fee payable under a subcontract will be in accordance with the provisions of Section ____.
(g) The Contractor shall give the Contracting Officer immediate written notice of any action or suit filed and prompt notice of any claim made against the Contractor by any subcontractor or vendor that, in the opinion of the Contractor, may result in litigation related in any way to this contract with respect to which the Contractor may be entitled to reimbursement from the Government.
(End of clause)
[58 FR 40381, July 28, 1993, as amended at 70 FR 41157, July 18, 2005]