The CO shall prepare the Schedule as follows:
(a) Section A, Solicitation/contract form. Use SF 1442, Solicitation, Offer, and Award (Construction, Alteration or Repair), as prescribed in FAR 36.701(a).
(b) Section B, Bid schedule. Bid schedule.
(c) Section C, Specifications/Drawings. Include specifications and drawings ( See FAR Part 11) or reference other location in the uniform contract format ( e.g. Section J, attachment ___).
(d) Section D, Packaging and Marking. Not applicable.
(e) Section E, Inspection and acceptance. Include inspection, acceptance, quality assurance, and reliability requirements ( See FAR Part 46).
(f) Section F, Deliveries or performance. Include Suspension of Work, Liquidated Damages, Commencement, Prosecution, and Completion of Work, Variation in Quantity clauses ( See FAR Part 12).
(g) Section G, Contract administration data. Include Contracting Officer's Representative/Technical Representative identification, and any required administration information ( e.g., accounting and appropriation data).
(h) Section H, Special contract requirements. Include any special contract requirements which are not included in other sections of the uniform contract format.