(a) The head of the contracting activity shall submit to the Procurement Executive a written request for each deviation from the FAR or the DOSAR, whether for individual cases, classes of cases, or deviations pertaining to treaties and executive agreements. Each request for a deviation shall state-
(1) The nature of the deviation requested, including whether it is an individual or class deviation;
(2) The FAR or DOSAR regulation from which the deviation is requested;
(3) The circumstances under which the deviation would be used;
(4) The effect intended by the deviation; and
(5) The expiration date recommended for the deviation.
(b) The head of the contracting activity shall also submit all pertinent documentation supporting the request.