Section 570.305: Two-phase design-build selection procedures.

(a) These procedures apply to acquisitions of leasehold interests if you use the two-phase design-build selection procedures authorized by 570.105-2.

(b) The SFO must include all the following information:

    (1) The Scope of Work.

    (2) The evaluation factors and subfactors to be used in evaluating phase-one proposals and their relative importance.

    (3) The maximum number of offerors to be selected to submit competitive proposals in phase-two.

    (4) The evaluation factors, including cost or price, and subfactors to be used in evaluating phase-two proposals and selecting the successful offeror, and their relative importance.

(c) The following procedures apply to phase-one evaluation factors:

    (1) Phase one factors include:

    (i) Specialized experience and technical competence.

    (ii) Capability to perform.

    (iii) Past performance of the offeror’s team (including architect-engineer and construction members of the team).

    (iv) Other appropriate factors, such as site or location.

    (2) Do not require offerors to submit detailed design information or cost or price information in phase one. Do not use cost related or price related evaluation factors.

(d) Set the maximum number of offerors to be selected for phase-two to not exceed five (5) unless you determine that a number greater than five is both:

    (1) In the government’s interest.

    (2) Consistent with the purpose and objectives of the two-phase selection process.

(e) In phase-two, require detailed technical and price proposals. Evaluate the proposals using the procedures in 570.306.