As prescribed in 342.7003-1(a), the Contracting Officer shall insert the following clause:
Withholding of Contract Payments (January 2006)
Notwithstanding any other payment provisions of this contract, failure of the Contractor to submit required reports when due or failure to perform or deliver required work, supplies, or services, may result in the withholding of payments under this contract unless such failure arises out of causes beyond the control, and without the fault or negligence of the Contractor as defined by the clause entitled “Excusable Delays” or “Default,” as applicable. The Government will immediately notify the Contractor of its intention to withhold payment of any invoice or voucher submitted.
(End of clause)