Upon receipt of information that a contractor's accumulated cost and projected expenditures will exceed the limit of funds obligated by the contract, the Contracting Officer shall coordinate immediately with the appropriate program office to determine whether the contract should be modified or terminated. If the Contracting Officer receives information from a source other than the contractor that a cost overrun is anticipated, the Contracting Officer shall verify the information with the contractor and remind the contractor of the notification requirements of the Limitation of Cost clause.