(b) Use the clause at FAR 52.211-12, Liquidated Damages-Construction, in all construction contracts exceeding $550,000, except cost-plus-fixed-fee contracts or contracts where the contractor cannot control the pace of the work. Use of the clause in contracts of $550,000 or less is optional.