Reference

More Resources

 

Section 211.274-3: Policy for valuation.

    (a) It is DoD policy that contractors shall be required to identify the Government’s unit acquisition cost (as defined in 252.211-7003(a)) for all items delivered, even if none of the criteria for placing a unique item identification mark applies.

    (b) The Government’s unit acquisition cost is-

      (1) For fixed-price type line, subline, or exhibit line items, the unit price identified in the contract at the time of delivery;

      (2) For cost-type or undefinitized line, subline, or exhibit line items, the contractor’s estimated fully burdened unit cost to the Government at the time of delivery; and

      (3) For items delivered under a time-and-materials contract, the contractor’s estimated fully burdened unit cost to the Government at the time of delivery.

    (c) The Government’s unit acquisition cost of subassemblies, components, and parts embedded in delivered items need not be separately identified.




Warning: require(/home/simplyauto/www/includes/site_footer.php): failed to open stream: Permission denied in /home/simplyauto/www/regs/fars/section.php on line 347

Fatal error: require(): Failed opening required '../../includes/site_footer.php' (include_path='.:/usr/local/lib/php') in /home/simplyauto/www/regs/fars/section.php on line 347