The contracting officer must take the following actions to determine whether a proposed contractual action requires a subcontracting plan:
(a) Determine whether the proposed contractual action will meet the dollar threshold in 19.702(a)(1) or (2). If the action includes options or similar provisions, include their value in determining whether the threshold is met.
(b) Determine whether subcontracting possibilities exist by considering relevant factors such as -
(1) Whether firms engaged in the business of furnishing the types of items to be acquired customarily contract for performance of part of the work or maintain sufficient in-house capability to perform the work; and
(2) Whether there are likely to be product prequalification requirements.
(c) If it is determined that there are no subcontracting possibilities, the determination must be approved at a level above the contracting officer and placed in the contract file.
(d) In solicitations for negotiated acquisitions, the contracting officer may require the submission of subcontracting plans with initial offers, or at any other time prior to award. In determining when subcontracting plans should be required, as well as when and with whom plans should be negotiated, the contracting officer must consider the integrity of the competitive process, the goal of affording maximum practicable opportunity for small business, veteran-owned small business, service-disabled veteran-owned small business, HUBZone small business, small disadvantaged business, and women-owned small business concerns to participate, and the burden placed on offerors.
(e) A contract may have no more than one plan. When a modification meets the criteria in 19.702 for a plan, or an option is exercised, the goals associated with the modification or option shall be added to those in the existing subcontract plan.